文字方塊: HKPFH Joint Venture

 

 


 

 

 

 

文字方塊: Contract No.: CV/2013/06
Handling of Surplus Public Fill 
(2014-2016)

TUEN MUN AREA 38 FILL BANK

MONTHLY EM&A REPORT NO.21

(21 TO 31 JANUARYFEBRUARY 2014)
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

Prepared by:                                                    

                          LAW, Sau Yee

                          Senior Environmental Officer

                    

                    
 
 

 

 

 

 

 

 

 

Checked by:                                                     

                         LAU, Chi Leung

                          Environmental Team Leader

                           

 
 

 


                                                                                                 

 

 

 

 

 

 

Issue Date: 1911 February March 2014                                           Report No.: ENA40347191

 
 

 


 

 

TABLE OF CONTENTS                                                                                                             Page

 

Executive SUMMARY

 

1.0

INTRODUCTION

1

2.0

PROJECT INFORMATION

 

 

2.1 Construction Programme

1

 

2.2 Project Organization and Management Structure

1

 

2.3 Contact Details of Key Personnel

1

3.0

Construction progress in this reporting month

2

4.0

Air Quality Monitoring

 

 

4.1 Monitoring Requirement

2

 

4.2 Monitoring Equipment

2

 

4.3 Monitoring Parameters, Frequency and Duration

2

 

4.4 Monitoring Locations and Schedule

2

 

4.5 Monitoring Methodology

3

 

4.6 Action and Limit levels

3 – 4

 

4.7 Event-Action Plans

4

 

4.8 Results and Observations

4

5.0

Marine water quality monitoring

 

 

5.1 Monitoring Requirements

4

 

5.2 Monitoring Locations

4

 

5.3 Monitoring Parameters and Frequency

4

 

5.4 Monitoring Methodology and Equipment Used

5 – 6

 

5.5 Action and Limit Levels

6

 

5.6 Event and Action Plan

7

 

5.7 Monitoring Duration and Period in this reporting month

7

 

5.8 Marine Water Monitoring Results

7

6.0

Noise Monitoring

 

 

6.1 Monitoring Requirements

7

 

6.2 Monitoring Equipment

8

 

6.3 Monitoring Parameters, Duration and Frequency

8

 

6.4 Monitoring Locations and Period

8

 

6.5 Monitoring Procedures and Calibration Details

8 – 9

 

6.6 Action and Limit levels

9

 

6.7 Event-Action Plans

9

 

6.8 Results and Observation

9

7.0

Environmental audit

 

 

7.1 Weekly Site Inspection

9 – 10

 

7.2 Review of Environmental Monitoring Procedures

10

 

7.3 Status of Environmental Licensing and Permitting

10

 

7.4 Implementation Status

11

8.0

Landscape and visual

11

9.0

Waste Management

 

 

9.1 Summary of Waste disposed of in this month

11

 

9.2 Advice on the Solid and Liquid Waste Management Status

12  

10.0

Environmenatl non-conformance

 

 

10.1 Summary of air quality, noise and marine water quality

12

 

10.2 Summary of Environmental Complaints

12

 

10.3 Summary of Notification of Summons and Prosecution

12

11.0

Conclusions and Recommentations

12 – 13  

12.0

Future key issue

14

 

 

 

 


 

 

APPENDIX

A

Organization Chart and Lines of Communication

B1

Calibration Certificates for Impact Air Quality Monitoring Equipments

B2

Impact Air Quality Monitoring Results

B3

Graphical Plots of Impact Air Quality Monitoring Data

C1

Calibration Certificates for Impact Marine Water Quality Monitoring Equipments

C2

Impact Marine Water Quality Monitoring Results

C3

Graphical Plots of Impact Marine Water Quality Monitoring Data

D1

Calibration Certificates for Impact Noise Monitoring Equipments

D2

Impact Noise Monitoring Results

D3

Graphical Plots of Impact Noise Monitoring Data

E

Weather Condition

 

F

Event-Action Plans

G

Construction Programme

H

Weekly ET’s Site Inspection Record

I

Implementation Schedule of Mitigation Measures

J

Site General Layout Plan

K

QA/QC Results of Laboratory Analysis

L

Complaint Log

 

 

Figures

 

Figure 1

Locations of Air Quality Monitoring StationsTuen Mun Area 38 Fill Bank

Figure 2

Locations of Water Quality Monitoring StationsTuen Mun Area 38 Fill Bank

Figure 3

Locations of Noise Quality Monitoring StationsTuen Mun Area 38 Fill Bank

 

 

Tables

 

2.1

Contact Details of Key Personnel

4.1

Air Quality Monitoring Equipment

4.2

Monitoring parameters, duration and frequency of air quality monitoring

4.3

Action and Limit levels for 24-hr TSP and 1-hr TSP

5.1

Monitoring Parameters and Frequency of the marine water

5.2

Summary of testing procedure

5.3

Details of Water Quality Monitoring Equipment (In-site measurement)

5.4

Water Quality Action and Limit Levels

5.5

Time Schedule of Water Quality Monitoring

5.6

Summary of Marine Water Quality Exceedances in this reporting month

6.1

Noise Monitoring Equipment

6.2

Duration, Frequencies and Parameters of Noise Monitoring

6.3

Action and Limit Levels for noise monitoring

7.1

Key Findings of Weekly ET Site Inspections in this reporting month

7.2

Summary of environmental licensing and permit status

7.3

Summary of Environmental Complaints and Prosecutions

9.1

Actual amounts of waste generated in this reporting month

 

 


 

Executive SUMMARY

 

 

This monthly Environmental Monitoring and Audit (EM&A) report No.21 was prepared by Environmental Team (ET) of ETS-Testconsult Ltd (ETL) for the “Contract No. CV/2013/06 Handling of Surplus Public Fill (2014-2016) Tuen Mun (TM) Area 38 Fill Bank” (The Project).

 

This report documented the findings of EM&A Works conducted during the operation phase of Fill Bank at TM Area 38 from 21 to 31 Januaryin February 2014.

 

 

Site Activities

 

As informed by the Contractor, the site activities in this reporting period were as below:

·       Removal of stockpiled Public Fill to Tipping Hall unloading point;

·       Operation of the TM Area 38 Fill Bank;

·       Collection and delivery of Public Fill  by  barges from the tipping halls at the TM Area 38 Fill Bank to the Tai Shan Reclamation site in Mainland; and

·       Construction of contractor's site office at area B3;

·       Upgrading of Surveillance Systems;

·       Construction of Wheel Washing Bay; and

·       Installation of Project Sign Board..

 

 

Environmental Monitoring Progress

 

The summary of the monitoring activities in this monitoring month is listed below:

 

·       24-hour TSP Monitoring: 25 Occasions at 2 designated locations

·       1-hour TSP Monitoring: 612 Occasions at 2 designated locations

·       Noise, Daytime: 48 Occasions at 2 designated locations

·       Marine Water Quality Monitoring: 511 Occasions at 4 designated locations

·       Weekly-site inspection: 24 Occasions

 

 

Air Monitoring

 

No exceedance of Action and Limit levels was recorded for 1-hr and 24-hr TSP monitoring in the reporting month.

 

 

Noise Monitoring

 

No exceedance of Action and Limit levels for noise monitoring was recorded in the reporting month.

 

 

Marine Water Quality Monitoring

 

According to the summary of marine water monitoring results, no exceedance of Action and Limit levels was recorded.

 

 

Weekly Site Inspection

 

In general, performance on environmental mitigation measures implemented was found to be satisfactory in this reporting month. The major findings observed during site inspections are presented in the Section 7.0.

 

Environmental Complaints, Notification of summons and successful prosecutions

 

No complaint, notification of summon and prosecution with respect to environmental issues was received in this monitoring month.

 

Future Key Issues

 

Based on the site inspections and forecast of engineering works in the coming month, key issues to be considered are as follows:

 

·       Dust generation from activities on site, such as vehicular movements along unpaved area and rock crushing activities;

·       Noise impact from operating equipment and machinery on site;

·       Wastewater and surface runoff from the site discharged into nearby water body; and

·       Storage and usage of chemicals / fuel and chemical waste / waste oil.

 


 

1.0          INTRODUCTION

 

HKPFH Joint Venture (HKPFH-JV) appointed Environmental Team (ET) of ETS-Testconsult Limited (ETL) to undertake the Environmental Monitoring and Audit (EM&A) for the Contract No: CV/2013/06Handling of Surplus Public Fill (2014-2016) – Tuen Mun (TM) Area 38 Fill Bank” (The Project).

 

In accordance with the Condition 5 of Part C of Environmental Permit (No.: EP-210/2005/B) (the EP), an EM&A programme as set out in the Project Profile should be implemented.

 

The EM&A programme requires environmental monitoring for air quality, water quality and environmental site inspections for air quality, water quality, landscape and visual, and waste management. The EM&A requirements for each parameter described in the following sections include:

 

§   All monitoring parameters;

§   Monitoring schedules for the reporting month and forthcoming months;

§   Action and Limit levels for all environmental parameters;

§   Event/Action Plans;

§   Environmental mitigation measures, as recommended in the Project Profile; and

§   Environmental requirements in contract documents.

 

Baseline monitoring was completed in May 2003 by Stanger Asia Ltd. Action and Limit Levels were established for air and water quality parameters based on the baseline monitoring results.

 

This report documented the findings of EM&A Works conducted during the operation phase of Fill Bank at Tuen Mun Area 38 from 21 to 31 Januaryin February 2014.

 

 

2.0          PROJECT INFORMATION

 

2.1          Construction Programme

 

Details of construction programme are shown in Appendix G.

 

2.2       Project Organization and Management Structure

 

The organization chart and lines of communication with respect to the on-site environmental management and monitoring program are shown in Appendix A.

 

2.3       Contact Details of Key Personnel

 

The key personnel contact names and telephone numbers are shown in Table 2.1.

 

Table 2.1           Contact Details of Key Personnel

Organization

Name of Key Staff

Project Role

Tel. No.

Fax No.

CEDD

Mr. P C Mok

Mr. K C Wong

Mr. C T Chock

Mr. Y F Kwong

Engineer’s Representative

2762 5514

2714 0113

IEC (ENVIRON)

Mr Tony Cheng

IEC

3465 2888

3465 2899

Contractor (HKPFH-JV)

Mr. K W Li

Project Manager

9750 6438

2744 6937

ET (ETL)

Mr C. L. Lau

ET Leader

2946 7791

2695 3944

 


 

3.0       Construction Progress in this reporting month

 

As informed by the Contractor, the activities in the reporting month include:

·       Removal of stockpiled Public Fill to Tipping Hall unloading point;

·       Operation of the TM Area 38 Fill Bank;

·       Collection and delivery of Public Fill  by  barges from the tipping halls at the TM Area 38 Fill Bank to the Tai Shan Reclamation site in Mainland;

·       Construction of contractor's site office at area B3;

·       Upgrading of Surveillance Systems;

·       Construction of Wheel Washing Bay; and

·       Installation of Project Sign Board.

·Removal of stockpiled Public Fill to Tipping Hall unloading point;

·Operation of the TM Area 38 Fill Bank;

·Collection and delivery of Public Fill  by  barges from the tipping halls at the TM Area 38 Fill Bank to the Tai Shan Reclamation site in Mainland; and

·Construction of contractor's site office at area B3.

 

 

4.0          AIR QUALITY MONITORING

 

4.1        Monitoring Requirement

 

1-hr and 24-hr TSP levels were monitored in the reporting month. Table 4.3 shows the Action and Limit Levels for the environmental monitoring works.

 

4.2        Monitoring Equipment

 

Both 1-hour and 24-hour TSP air quality monitoring was performed using a GMWS2310 High Volume Air Sampler (HVS) located at each of the designated monitoring station. Table 4.1 summarizes the equipment used in the air quality monitoring programme. Copies of the calibration certificates for the HVS and calibrator are attached in Appendix B1.

 

Table 4.1           Air Quality Monitoring Equipment

Equipment

Model and Make

HVS

Greasby GMWS2310

Calibrator

Tisch TE-5025A

 

4.3        Monitoring Parameters, Frequency and Duration

 

Table 4.2 summarizes the monitoring parameters, monitoring duration and frequencies of air quality monitoring.

 

            Table 4.2           Monitoring parameters, duration, frequency of air quality monitoring

Parameter

Duration

Frequency

24-hr TSP

24 hr

Once per six days

1-hr TSP

1 hr

Three times per six days

 

4.4        Monitoring Locations and Schedule

 

In accordance with the Project Profile, two air-quality monitoring stations, namely TM-A1 and TM-A2, were selected for the 1-hr TSP and 24-hr TSP sampling.

 

Since the area for existing air monitoring station TM-A2 near Tipping Hall No.1 was handed over to EcoPark, air monitoring station TM-A2 was cancelled and the air monitoring was carried out at an alternative air monitoring station TM-RA2 (refer to Figure 1 attached) from 28 October 2008.

 

The locations of monitoring stations are shown in Figure 1.

 

During the reporting month, 1-hr and 24-hr TSP monitoring were carried out as the schedule. The details for 24-hr and 1-hr TSP monitoring carried out in this reporting month are summarized in Appendix B2.


 

4.5        Monitoring Methodology

 

Both 1-hr and 24-hr air quality monitoring (High Volume Sampler)

 

Instrumentation

High volume sampler, as HVS, (Greasby GMWS2310) complete with appropriate sampling inlets were employed for both 1-hour and 24-hour TSP monitoring. The sampler is composed of a motor, a filter holder, a flow controller and a sampling inlet and its performance specification complies with that required by USEPA standard Title 40, Code of Federation Regulations Chapter 1 (Part 50).

 

Installation

The installation of HVS refers to the requirement stated in Appendix D2 “General Technical Requirements of Environmental Monitoring” in the Environmental Monitoring and Audit Guidelines for Development Projects in Hong Kong published by EPD.

 

Operation/Analytical Procedures

Operating/analytical procedures for the operation of HVS are as below:

 

·          Prior to the commencement of the dust sampling, the flow rate of the high volume sampler was properly set (between 0.6m3/min and 1.7m3/min.) in accordance with the manufacturer’s instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50. The flow rate is indicated on the flow rate chart.

·          For TSP sampling, fiberglass filters (GA-55) were used.

·          The power supply was checked to ensure the sampler worked properly.

·          On sampling, the sampler was operated 5 minutes to establish thermal equilibrium before placing any filter media at designated air monitoring station.

·          The filter holding frame was then removed by loosening the four nuts and carefully a weighted and conditioned filter was centered with the stamped number upwards, on a supporting screen.

·          The filter was aligned on the screen so that the gasket formed an air-tight seal on the outer edges of the filter.  Then the filter holder frame was tightened to the filter holder with swing bolts. The applied pressure should be sufficient to avoid air leakage at the edges.

·         The programmable timer will be set for a sampling period of 1 hour / 24 hours. Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number.).

·         After sampling, the filter was transferred from the filter holder of the HVS to a sealed plastic bag and sent to the laboratory for weighting.  The elapsed time was also recoded.

·         Before weighting, all filters were equilibrated in a desiccator for 24 hour with the temperature of 25oC + 3oC and the relative humidity (RH) <50% +5%.

 

Maintenance & Calibration

 

·          The HVS and their accessories should be maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.

·          HVS should be calibrated at bi-monthly intervals.

 

            Wind Data Monitoring

 

Wind data included wind speed and wind direction were directly extracted from Tuen Mun Station of Hong Kong Observatory during this reporting month. The wind data are presented in Appendix E.

 

4.6        Action and Limit Levels

 

Table 4.3 shows the Action and Limit levels for 24-hr TSP and 1-hr TSP monitoring.


 

Table 4.3           Action and Limit Levels for 24-hr TSP and 1-hr TSP

Monitoring Location

24-hr TSP (mg/m3)

1-hr TSP (mg/m3)

Action Level

Limit Level

Action Level

Limit Level

TM-A1

192

260

344

500

TM-RA2 *

192

260

344

500

Remark (*): Since the area for existing air monitoring station TM-A2 near Tipping Hall No.1 was handed over to EcoPark, air monitoring station TM-A2 was cancelled and the air monitoring was carried out at an alternative air monitoring station TM-RA2 from 28 October 2008. Since dust monitoring stations TM-A2 and TM-RA2 are located close to the major dust emission sources and no significant difference between them on the prevailing meteorological conditions, the baseline data from TM-A2 can also be valid in the case of TM-RA2.

 

4.7        Event-Action Plans

 

Please refer to Appendix F for details.

 

4.8        Results and Observations

 

Totally 52 occasions of 24-hr TSP monitoring and 126 occasions of 1-hr TSP monitoring were carried out in this reporting period. All monitoring data of both 1-hr and 24-hr TSP monitoring is provided in Appendix B2. Graphical presentation of 1-hr and 24-hr TSP monitoring results for the reporting month is shown in Appendix B3. Wind data, including wind speed and wind direction, are annexed in Appendix E.

 

No exceedance of Action and Limit level was recorded for 1-hr and 24-hr TSP monitoring in the reporting month.

 

Generally, the Contractor implemented sufficient dust mitigation measures, including operation of wheel washing facilities and road dampening by water bowsers on the main haul roads and unpaved areas.

 

 

5.0          MARINE WATER QUALITY MONITORING

 

5.1       Monitoring Requirements

 

In accordance with the Project Profile, impact marine water quality monitoring was conducted three days per week. Measurements were taken at both mid-flood and mid-ebb tides at three depths (i.e. 1m below surface, mid depth and 1m from seabed) at two control monitoring stations (TM-FC1 and TM-FC2) and two impact monitoring stations (TM-FM1and TM-FM2).

 

5.2        Monitoring Locations

 

As stipulated in the EM&A requirement, there were four monitoring stations undertaken during the impact monitoring. Figure 2 shows the locations of the marine water quality monitoring stations.

 

5.3        Monitoring Parameters and Frequency

 

Monitoring of the marine water quality parameters and frequency are listed in Table 5.1.

 

Table 5.1           Monitoring Parameters and Frequency of the marine water

Monitoring Station

Parameter

Frequency

No. of Depths

Control Stations:

TM-FC1 (Mid-ebb) and TM-FC2 (Mid-flood)

 

Impact Stations:

TM-FM1 and TM-FM2

Depth (m)

3 days/week,

2 tides/day

3

(Surface, mid-depth & bottom)

Temperature (°C)

Dissolved Oxygen

(mg/L and % saturation)

Turbidity (NTU)

Salinity (ppt)

Suspended solids (mg/L)


 

5.4          Monitoring Methodology and Equipment Used

 

For Location of the monitoring stations

 

Global Positing System (GPS)

A hand-held digital GPS was used to identify the designated monitoring stations prior to water sampling.

 

For Water Depth measurement

 

Echo Sounder

A portable, battery-operated echo sounder was used for the determination of water depth at each designated monitoring station.

 

For In-situ Water Quality Measurement

 

All in-situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals or sometimes longer throughout all stages of the water quality monitoring.

 

Dissolved Oxygen, Salinity and Temperature Measuring Equipment

A portable, weatherproof dissolved oxygen & salinity measuring instrument, which complete with cable, sensor and DC power source (e.g. YSI 85 or equivalent) was used for measuring:

·       a dissolved oxygen level in the range of 0-20 mg/L and 0-200 % saturation;

·       a salinity in range 0-40 ppt; and

·       a temperature of 0-45 degree Celsius

 

A membrane electrode with automatic temperature compensation complete with a cable was installed.

 

Turbidity Measurement Instrument

A portable and weatherproof turbidity meter (HACH model 2100Q) was used during impact monitoring. It has a photoelectric sensor capable of measuring turbidity between 0-1000 NTU. Response of the sensor was checked with certified standard Turbidity solutions before the start of measurement.

 

For Water Sampling and Sample Analysis

 

In-situ monitoring was carried out at three depths: 1 meter below water surface, at mid-depth and 1 meter above the seabed. At each sampling depth, duplicate readings of dissolved oxygen content and turbidity were taken.  The probes were retrieved out of the water after first measurement and then redeployed for the second measurement.  The difference between the two readings of each set was more than 25% of the value of the first reading while a third measurement would be conducted to ensure data precision.

 

Water Sampler

A water sampler comprising a transparent PVC cylinder, with a capacity of not less than 2 liters, was lowered into the water body at the predetermined depth. The both opening ends of the sampler were then closed accordingly by dead weight and water samples were collected.

 

Water Container

The sample container, made by high-density polythene, was rinsed with a portion of the water sample. The water sample was then transferred to the container, labeled with a unique sample ID and sealed with a screw cap. The water samples were stored in a cool box maintained at 4oC. The water samples were then delivered to a local HOKLAS-accredited laboratory (Environmental Laboratory, ETS-Testconsult Ltd, HOKLAS Registration No. 022) on the same day for analysis.


 

The summary of testing method of testing parameter as recommended by EIA or required by EPD, with the QA/QC results in accordance with the requirement of HOKLAS or international accredited scheme is shown in Table 5.2. For the QA/QC procedures, one QC sample, one duplicate sample and one sample spike of every batch of 20 samples were analysis. The QA/QC results are summarized in Appendix K.

 

Table 5.2           Summary of testing procedure

Laboratory Analysis

Testing Procedure

Detection Limit

Total suspended solids

In house method based on APHA 19th ed 2540D

1.0 mg/L

 

In-situ measurement

 

All in-situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use. Responses of sensors and electrodes were checked with certified standard solutions before each use. Wet bulb calibration for a DO meter was carried out before the start of measurement.

 

At each measurement/sampling depth, two consecutive measurements of dissolved oxygen (DO), dissolved oxygen saturation (DOS), turbidity and salinity were taken. For turbidity measurement, the sample was collected by using sampler and then transferred to the cell. The reading of turbidity of the sample was directly recorded from the Turbidimeter (HACH 2100Q) after inserting the cell to the Turbidimeter. For DO, DOS and Salinity, measurements were conducted three days per week at both mid-ebb and mid-flood tides at three depths (i.e. 1m below surface, mid depth and 1m from seabed). The duplicate measurements were averaged if the difference was not greater than 25%. If the difference is greater than 25%, repeat measurement will be required to be carried out.

 

Table 5.3 shows the equipment used for in-situ monitoring of water quality. The calibration certificates are attached in Appendix C1.

 

Table 5.3           Details of Marine Water Quality Monitoring Equipment (In-site measurement)

Parameter

Model

Date of Calibration

Due Date

Equipment No.

Coordinate of Monitoring stations

Garmin eTrex 10

-----

-----

ET/EW/005/04

Dissolved Oxygen (Saturation), Temperature, Salinity

YSI Dissolved Oxygen, Salinity & Temperature Meter, YSI Pro 2030

29/10/13

29/01/04

28/01/14

28/04/14

ET/EW/008/004 *

Turbidity

HACH Model 2100Q Turbid Meter

07/01/14

06/04/14

ET/0505/010 *

Water Depth

Speedtech SM-5

-----

-----

ET/EW/002/06

Remark:(*) indicates the instrument should be calibrated on use.

 

5.5        Action and Limit Levels

 

The water quality criteria, namely Action and Limit (A/L) levels are presented in the table below.

 

Table 5.4           Water Quality Action and Limit Levels

Parameter

Action Level

Limit Level

DO (mg/L)

Surface & Middle

<4.78 mg/L (5%-ile of baseline data)

Bottom

<4.16 mg/L (5%-ile of baseline data)

Surface & Middle

<4.00 mg/L (1%-ile of baseline data)

Bottom

<2.00 mg/L

SS (mg/L)

(Depth-averaged)

>120% of the upstream control station’s SS at the same tide on the same day

>130% of the upstream control station’s SS at the same tide on the same day

Turbidity (NTU)

(Depth-averaged)

>120% of the upstream control station’s turbidity at the same tide on the same day

>130% of the upstream control station’s turbidity at the same tide on the same day


 

5.6          Event and Action Plan

 

Please refer to the Appendix F for details. 

 

5.7          Monitoring Duration and Period in this reporting month

 

Totally 5 occasions of marine water quality monitoring were carried out in this reporting period. Below is the time schedule for the marine water quality monitoring events that were conducted in this reporting period:

 

Table 5.5       Time Schedule of Marine Water Quality Monitoring

February 2014

 

Sunday

Monday

Tuesday

Wednesday

Thursday

Friday

Saturday

 

 

 

 

 

 

 

1

 

 

2

 

3

 

4

5

 

6

7

 

8

 

9

 

10

 

11

12

 

13

14

 

15

 

16

 

17

 

18

19

 

20

21

 

22

 

23

 

24

 

25

26

 

27

28

 

 

 

January 2014

 

Sunday

Monday

Tuesday

Wednesday

Thursday

Friday

Saturday

 

 

 

21

22

 

23

24

 

25

 

26

 

27

 

28

29

 

30

31

 

 

 

 

Remark  (▼) :  Marine water quality monitoring carried out by ET

 

The duration of marine water quality monitoring is detailed in Appendix C2.

 

5.8          Marine Water Quality Monitoring Results

 

The impact water quality measurement results are detailed in Appendix C2. Appendix C3 presents the water quality monitoring data and graphical presentations of monitoring results respectively.

 

The summary of marine water quality exceedances is shown in Table 5.6.

 

Table 5.6           Summary of Marine Water Quality Exceedances in this reporting month

Tide

Station

Exceedance Level

DO

Turbidity

SS

Total

Surface & Middle

Bottom

Mid-Ebb

TM-FM1

Action

0

0

0

0

0

Limit

0

0

0

0

0

TM-FM2

Action

0

0

0

0

0

Limit

0

0

0

0

0

Mid-Flood

TM-FM1

Action

0

0

0

0

0

Limit

0

0

0

0

0

TM-FM2

Action

0

0

0

0

0

Limit

0

0

0

0

0

Total

Action

0

0

0

0

0

Limit

0

0

0

0

0

 

According to the summary of marine water monitoring results, no exceedances of Action and Limit levels were recorded for this reporting month.

 

 

6.0       Noise Monitoring

 

6.1       Monitoring Requirements

 

Noise monitoring was conducted at 2 designated monitoring stations as specified in the Sections 26.10 to 26.12 of the Particular Specification for good site practice.

 

The equipment, parameter, frequency, duration, methodology, calibration details, results and observations of the noise monitoring for the reporting month are presented in this section.


 


 

6.2        Monitoring Equipment

 

An Integrating Sound Level Meter was used for noise monitoring. It was a Type 1 sound level meter capable of giving a continuous readout of the noise level reading including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). It complies with International Electro Technical Commission Publications 651:1979 (Type1) and 804:1985 (Type1), and speed in m/s was used to monitor the wind speed.

 

Table 6.1 summarizes noise monitoring equipment model being used. A copy of the calibration certificate for noise meter and calibrator are attached in Appendix D1.

 

Table 6.1           Noise Monitoring Equipment

Equipment

Model

Sound Level Meter

Rion NL-31 / Rion NL-52

Calibrator

Rion NC-73 / Castle GA607

 

6.3        Monitoring Parameters, Duration and Frequency

 

Duration, frequencies and parameters of noise measurement are presented in Table 6.2.

 

Table 6.2           Duration, Frequencies and Parameters of Noise Monitoring

Time period

Duration/min

Parameters

Frequency

Day-time: 0700-1900 hrs

on normal weekday

30

Leq, L10, L90

Twice per week

 

6.4       Monitoring Locations and Period

 

Since Lands Dept did not approve to carry out noise monitoring at their own area where the noise monitoring stations TM-N1 and TM-N2 located due to the security, noise monitoring carried out at two noise monitoring stations TM-RN1 and TM-RN2 (refer to the figure 3 attached) from 18 December 2007.

 

The noise monitoring locations, TM-RN1 and TM-RN2 are shown in Figure 3. The noise measurement at TM-RN1 and TM-RN2 are façade measurement.

 

The noise-monitoring period of monitoring stations is summarized in Appendix D2.

 

6.5        Monitoring Procedures and Calibration Details

 

Operation/Analysis Procedures

 

·         The Sound Level Meter was set on a tripod at a height of 1.2m above the ground.

·         For free field measurement, the meter was positioned away from any nearby reflective surfaces.

·         The battery condition was checked to ensure the correct functioning of the meter.

·         Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

-          Frequency weighting:  A

-          Time weighting         :  Fast

-           Time measurement  :  30 min

·          Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1000HZ.  If the difference in the calibration level before and after measurement was more than 1dB(A), the measurement would be considered invalid and repeat measurement would be required after re-calibration or repair of the equipment.

·         The wind speed was frequently checked with a portable wind meter.

·         During the monitoring period, the Leq, L10 and L90 were recorded.  In addition, site conditions and noise sources were recorded on a standard record sheet.

·         Free Field correction to the measurements should be made. Correction factor of +3dB(A) should be made to the free Field measurements. Noise monitoring would be cancelled in the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind gusts exceeding 10m/s.


 

Maintenance and Calibration

 

·         The microphone head of the sound level meter and calibrator are cleaned with soft cloth in quarterly intervals.

·         The meter is sent to the supplier or HOKLAS laboratory to check and calibrated in yearly intervals.

 

6.6        Action and Limit Levels

 

The Action and Limit levels for noise levels derived as illustrated in Table 6.3.

 

Table 6.3           Action and Limit Levels for noise monitoring

Time Period

Action *

Limit *

0700-1900 hrs on normal weekdays

When one documented complaint is received

65 dB(A)

 

6.7        Event-Action Plans

 

Please refer to the Appendix F for details.

 

6.8          Results and Observation

 

Totally 84 occasions of noise monitoring were carried out in this reporting month. The detail of the noise monitoring is provided in Appendix D2. Graphical presentation of the monitoring result for the reporting month is shown in Appendix D3.

 

Since no documented complaint on noise issue was received in this reporting month, no Action Level exceedance was recorded. Besides, no exceedance in Limit Level was recorded according to the result from Day-time noise monitoring.

 

The major sources of noise pollution observed in this reporting month were noise from the traveling dump trucks and from the operation of site machines.

 

 

7.0          Environmental Audit

 

7.1       Weekly ET Site Inspection

 

Weekly site inspections were carried out by ET to monitor the timely implementation of proper environmental pollution control and mitigation measures for the Project. In this reporting month, two four weekly site inspections were conducted on 06, 13, 20 and 24 February 23 and 29 January 2014. Summaries of key findings of weekly ET site inspections in this month are described in Table 7.1.

 

Table 7.1        Key Findings of Weekly ET Site Inspections in this reporting month

Date

Key Findings

Action(s) Taken recommended by ET

Action(s) Taken by the Contractor during the site audit

Rectification Status by ET

23 06 JanuaryFebruary 2014

C&D waste, such paper and idle buckets, were found discarded at water truck filling station. (Previous item)Several buckets of waste oil were found discarded at water truck filling station. (New item)

To collect and dispose of the water properly.To collect and store / dispose of the waste oil properly.

C&D waste, such paper and idle buckets, discarded at water truck filling station were cleared.---

ClosedFollow-up

Oil stain was noted from a generator at dry soil deposition area. (New item)Mud and silt were found accumulated inside the main drainage channel near tipping hall No.3. (New item)

To clear the oil stain and treat the contaminated material as chemical waste.To clear the accumulated mud and silt to avoid any blockage.

---

Follow-up

Skirt curtain for a generator at dry soil deposition area was dirty. (New item)

To replace the dirt skirt curtain by clean one.

---

Follow-up

0613 February 2014

Oil stain was noted from a generator at dry soil deposition area. (Previous item)

To clear the oil stain and treat the contaminated material as chemical waste.

---

Follow-up


 

Date

Key Findings

Action(s) Taken recommended by ET

Action(s) Taken by the Contractor during the site audit

Rectification Status by ET

13 February 2014

Skirt curtain for a generator at dry soil deposition area was dirty. (Previous item)

To replace the dirt skirt curtain by clean one.

---

Follow-up

0620 February 2014

Oil stain was noted from a generator at dry soil deposition area. (Previous item)

To clear the oil stain and treat the contaminated material as chemical waste.

Oil stain noted from a generator at dry soil deposition area was cleaned up.

Closed

Skirt curtain for a generator at dry soil deposition area was dirty. (Previous item)

To replace the dirt skirt curtain by clean one.

Clean skirt curtain for a generator at dry soil deposition area was used.

Closed

The enclosure of tipping hall No.2 was damaged. (New item)

To repair the damaged part of tipping hall properly.

---

Follow-up

24 February 2014

The enclosure of tipping hall No.2 was damaged. (Previous item)

To repair the damaged part of tipping hall properly.

The damaged enclosure of tipping hall No.2 was repaired.

Closed

29 January 2014

Several buckets of waste oil were found discarded at water truck filling station. (Previous item)

To collect and store / dispose of the waste oil properly.

The discarded buckets of waste oil at water truck filling station were collected.

Closed


 

Date

Key Findings

Action(s) Taken recommended by ET

Action(s) Taken by the Contractor during the site audit

Rectification Status by ET

29 January 2014

Mud and silt were found accumulated inside the main drainage channel near tipping hall No.3. (Previous item)

To clear the accumulated mud and silt to avoid any blockage.

Mud and silt accumulated inside the main drainage channel near tipping hall No.3 were cleared.

Closed

C&D waste, such paper and idle buckets, were found discarded at water truck filling station. (New item)

To collect and dispose of the water properly.

---

Follow-up

 

7.2          Review of Environmental Monitoring Procedures

 

The monitoring works conducted by the ET were inspected internally on a regular basis. The following observations have been recorded for the monitoring works:

 

Air Quality Monitoring

 

§  The monitoring team recorded the observations around the monitoring stations within and outside of the construction site.

§  The monitoring team recorded the temperature, air pressure and general weather condition on the monitoring day.

 

Water Quality Monitoring

 

§  The monitoring team recorded the observations around the monitoring stations, which might affect the results; and

§  Major water pollution sources were identified and recorded.

 

Noise Monitoring

 

§  The monitoring team recorded the observations around the monitoring station, which might affect the results.

§  Major noise sources were identified and recorded.

 

7.3          Status of Environmental Licensing and Permitting

 

All permits/licenses valid in this reporting month are summarized in Table 7.2.

 

Table 7.2     Summary of environmental licensing and permit status

Description

Permit No.

Valid Period

Section

From

To

Environmental Permit

EP-210/2005/B

08/04/13

---

Issued

Marine Dumping Permit

EP/MD/14-119

21/01/14

31/03/14

Approval for dumping 2,800,000  tons (approximately equal to 1,555,555 cu.m. bulked quantity) of Public Fill (Reclamation Materials) from Tseung Kwan O Area 137 Fill Bank and Tuen Mun Area 38 Fill Bank to designated dumping area at Guanghaiwan of Taishan


 

Description

Permit No.

Valid Period

Section

From

To

Chemical Waste Producer

5296-421-H3555-01

21/01/14

---

Spent battery containing heavy metals and spent lubricating oil

Billing Account for Waste Disposal

7018998

---

---

---

Effluent Discharge License

Application in progress


 

7.4          Implementation Status

 

7.4.1     Implementation Status of Environmental Mitigation Measures

 

An updated summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Appendix I. Most of the necessary mitigation measures were implemented properly.

 

7.4.2       Implementation Status of Event and Action Plan

 

No exceedance of Action and Limit levels was recorded for 1-hr and 24-hr TSP monitoring in the reporting month.

 

Apart from this, there was no exceedance on noise and marine water monitoring parameters recorded in this monitoring month. Hence no further actions were required.

 

7.4.3     Implementation Status of Environmental Complaint, Notification of Summon and Successful Prosecution Handling

 

No complaint, notification of summon and prosecution with respect to environmental issues was received in this monitoring month.

 

A summary of environmental complaints, notifications of summons and successful prosecutions was given in Table 7.3.

 

Table 7.3           Summary of Environmental Complaints and Prosecutions

Complaints logged

Summons served

Successful Prosecution

January February 2014

Cumulative

February 2014January 2014

Cumulative

February 2014January 2014

Cumulative

0

0

0

0

0

0

 

 

8.0          Landscape and Visual

 

Landscape and visual site audit was carried out on a weekly basis to monitor environmental issues in order to ensure that all mitigation measures were implemented timely and properly. The findings in this reporting month were:

 

§  The maximum stockpiling height at the Fill Bank was limited to a maximum of +40 mPD;

§  The Contractor hydroseeded the outer slopes of the Fill Bank as far as practicable;

§  The Contractor removed the stockpile of public fill in a sequence to allow the outer hydroseeded to be removed later than other portions as far as practicable; and

§  Lighting was set to minimize night-time glare.

 

 

9.0       Waste Management

 

9.1          Summary of Waste disposed of in this month

 

The actual amounts of different types of waste disposed of by the activities of the Project in the month are shown in Table 9.1


 

Table 9.1        Actual amounts of Waste generated in this reporting month

Waste Type

Actual Amount

Disposal Locations

Public Fill (m3)

110

---Tuen Mun 38 Fill Bank

C&D Waste (general refuse) (kg)

171300

WENT Landfill

Chemical Waste (kg/L)

0

---Collected by licensed collector

 


 

9.2          Advice on the Solid and Liquid Waste Management Status

 

The Contractor should provide sufficient preventive measures during equipment maintenance works so as to avoid oil leakage on the ground. In the event of any oil leakage, the Contractor should clean up the polluted soil and handle all the materials used for this cleaning works as chemical waste.

 

The drain outlet of all the bunded areas should be plugged properly. Besides, pre-cast drip trays were provided for oil drums at several areas, such as workshop and chemical storage area. The Contractor should collect and dispose of any stagnant water accumulated in the concrete bunding and drip trays and handle them as chemical waste.

 

The Contractor should use suitable containers with proper labels to store chemical wastes in accordance with Code of Practice on the Packaging, Labeling and Storage of Chemical Waste.  The Contractor should also advise their workers of the proper procedures in handling the chemical waste. All the trip tickets for chemical waste disposal should be properly kept in the site office.

 

The Contractor was reminded to increase the frequency of inspection and cleaning of the site drainage system, including permanent desilting chambers, desilting facilities, oil interceptor bypass tank and all the trapezoidal channels. Moreover, the Contractor should apply approved pesticides in the stagnant water ponds.

 

All the runoff from the parking area should be pumped to the desilting facilities and oil interceptors to remove suspended solids and oil & grease prior to discharge.

 

 

10.0      Environmental Non-conformance

 

10.1      Summary of air quality, noise and marine water quality

 

No exceedance of Action and Limit levels was recorded for 1-hr and 24-hr TSP monitoring in the reporting month.

 

According to the summary of marine water monitoring results, no exceedance of Action and Limit levels was recorded for this reporting month.

 

The noise level measured at the monitoring station complied with the Limit Level of 65dB(A). No complaint was received regarding noise issue in this reporting month.

 

10.2      Summary of Environmental Complaints

 

No complaint was occurred in this reporting month.

 

10.3      Summary of Notification of Summons and Prosecution

There was no notification of summon and prosecution respect to environmental issues registered in this reporting month.

 

 

11.0      Conclusions and recommendations

 

Conclusions

 

Impact monitoring of air quality, noise and water quality were carried out at designated locations in this reporting month.


 

 

According to the summary of air monitoring results, no exceedance of Action and Limit levels was recorded for 1-hr and 24-hr TSP monitoring in the reporting month.

 

According to the summary of marine water monitoring results, no exceedance of Action and Limit levels was recorded in this reporting month.


 

The noise level measured at the monitoring station complied with the Limit Level of 65dB(A). No complaint was received regarding noise issue in this reporting month.

 

According to the weekly site inspections carried out in this reporting month, the Contractor generally implemented sufficient dust mitigation measures, including operation of the mist spraying systems and automatic wheel washing facilities, dampening of haul roads and stockpiling areas.

 

No complaint, prosecution or notification of summons was received in this reporting month.

 

Recommendations

 

According to the environmental site inspections performed in the reporting month, the following recommendations were provided:

 

Air Quality

§  Ensure the frequency of water spraying on haul roads, unloading areas and stockpiles to be sufficient to suppress the dust sources;

§  Provide proper maintenance for the powered mechanical equipment and barges to avoid emission of dark smoke;

§  Provide water spraying onto the truckloads during inspection of fill material;

§  Conduct road sweeping on all paved haul roads and public roads especially outside and near the site egress by the road sweeper. Undertake water spraying on stockpiling area by water bowers;

§  Erect adequate speed limit signs to advise the truck drivers of the speed limit;

§  Operate mist spraying systems and automatic water sprinklers in the Fill Bank;

§  Implement the dust mitigation measures for the construction activities;

§  Designate proper haul roads to ensure effective water spraying; and

§  Ensure all vehicles to be washed before leaving the site egress by provision, operation and maintenance of automatic wheel washing facilities.

 

Noise

§  Conduct noisy activities at a farther location from the NSRs.

 

Water Quality

§  Maintain the drainage system, including the trapezoidal channels and permanent desilting chambers regularly; and

§  Remove the stagnant water or provide approved pesticides for the stagnant water in the permanent desilting chambers, if any.

 

Chemical and Waste Management

§  Remove waste materials from the site to avoid accumulation regularly;

§  Handle and store chemical wastes properly;

§  Remove unwanted material in the existing stockpiles and avoid further dumping of such material;

§  Provide and maintain sufficient drip trays for diesel drums, chemical containers, chemical waste storage drums and diesel operated generator set;

§  Maintain good housekeeping at the workshop area;

§  Ensure sufficient tarpaulin sheets are provided to cover drip trays; and

§  Avoid soil being polluted during oil filling and equipment maintenance; hence, properly remove and store the contaminated soil, if any.


 

Landscape and Visual

§  Provide hydroseeding on the exposed slopes, on which the final profile has been formed;

§  Erect all the site hoarding/chaining fences in accordance with agreed design at proper location; and

§  Maintain the hydroseeded slopes properly.

 


 

12.0      Future Key Issues

 

Based on the site inspections and forecast of engineering works in the coming month, key issues to be considered are as follows:

§  Dust generation from activities on site, such as vehicular movements along unpaved area and rock crushing activities;

§  Noise impact from operating equipment and machinery on site and

§  Wastewater and surface runoff from the site discharged into nearby water body.

 

 

 

 

- END OF REPORT -

Storage and usage of chemicals / fuel and chemical waste / waste oil.


 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix A

 

 

Project Organization Chart

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix B1

 

Calibration Certificates for

Impact Air Quality Monitoring Equipments

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix B2

 

Impact Air Quality Monitoring Results

 

 


 

 

 

Summary of 24-hr TSP Monitoring Results

 

 

 

 

Monitoring Station                         :    TM-A1

 

Start

Finish

Elapse Time

Sampling Time (hrs)

Flow Rate (m3/min.)

Average (m3/min.)

Filter Weight (g)

Conc. (mg/m3)

Date

Time

Date

Time

Initial

Final

Initial

Final

Initial

Final

2104/01/1402/14

134:030

05/02/1422/01/14

134:300

2109145.98

2111569.98

24.00

1.1033

1.1033

1.1033

2.73972.7502

2.95092.9874

133149

1027/01/1402/14

0914:005

11/02/1428/01/14

0914:005

2111771.98

2114195.98

24.00

1.1033

1.1033

1.1033

2.76272.7488

2.97392.9523

133128

16/02/14

09:00

17/02/14

09:00

21198.98

21222.98

24.00

1.1033

1.1033

1.1033

2.7420

2.9504

131

22/02/14

09:25

23/02/14

09:25

21226.98

21250.98

24.00

1.1033

1.1033

1.1033

2.7434

2.9296

117

28/02/14

09:00

01/03/14

09:00

21252.98

21276.98

24.00

1.1033

1.1033

1.1033

2.7312

2.9252

122

 

 

 

 

Monitoring Station                         :    TM-RA2

 

Start

Finish

Elapse Time

Sampling Time (hrs)

Flow Rate (m3/min.)

Average (m3/min.)

Filter Weight (g)

Conc. (mg/m3)

Date

Time

Date

Time

Initial

Final

Initial

Final

Initial

Final

04/02/1421/01/14

134:4000

05/02/1422/01/14

143:0040

2112781.98

2112051.98

24.00

1.2425

1.2425

1.2425

2.75282.7523

2.98712.9874

131131

10/02/1427/01/14

0914:010

11/02/1428/01/14

0914:010

21152073.98

21177231.98

24.00

1.2425

1.2425

1.2425

2.74932.7512

2.95772.9489

116110

16/02/14

09:00

17/02/14

09:00

21234.98

21258.98

24.00

1.2425

1.2425

1.2425

2.7367

2.9644

127

22/02/14

09:30

23/02/14

09:30

21262.98

21286.98

24.00

1.2425

1.2425

1.2425

2.7292

2.9071

99

28/02/14

09:00

01/03/14

09:00

21288.98

21312.98

24.00

1.2425

1.2425

1.2425

2.7406

2.9211

101

 


Summary of 1-hr TSP Monitoring Results  

 

 

Monitoring Station                              :        TM-A1                                                               

Date

Time

Elapse Time

Sampling Time (hrs)

Flow Rate (m3/min.)

Average (m3/min.)

Filter Weight (g)

Conc. (mg/m3)

Start

Finish

Initial

Final

Initial

Final

Initial

Final

2104/01/1402/14

0913:00

104:00

21090.144.98

21145091.98

1.00

1.1033

1.1033

1.1033

2.75272.7487

2.76872.7655

242254

0623/01/1402/14

143:405

154:405

2111569.98

2111670.98

1.00

1.1033

1.1033

1.1033

2.76222.7453

2.77962.7589

263205

0825/01/1402/14

10:00

11:00

2111670.98

211171.98

1.00

1.1033

1.1033

1.1033

2.75922.7554

2.77492.7681

237192

1128/01/1402/14

104:3005

151:3005

2114195.98

2114296.98

1.00

1.1033

1.1033

1.1033

2.76292.7514

2.77722.7666

216230

1328/01/1402/14

1309:0045

1410:0045

2114296.98

2114397.98

1.00

1.1033

1.1033

1.1033

2.76352.7525

2.77932.7686

239243

1530/01/1402/14

101:00

112:00

2114397.98

2114984.98

1.00

1.1033

1.1033

1.1033

2.75492.7498

2.76862.7669

207258

18/02/14

08:55

09:55

21222.98

21223.98

1.00

1.1033

1.1033

1.1033

2.7227

2.7369

215

18/02/14

10:15

11:15

21223.98

21224.98

1.00

1.1033

1.1033

1.1033

2.7631

2.7761

196

20/02/14

08:45

09:45

21224.98

21225.98

1.00

1.1033

1.1033

1.1033

2.7448

2.7589

213

22/02/14

08:20

09:20

21225.98

21226.98

1.00

1.1033

1.1033

1.1033

2.7702

2.7826

187

25/02/14

09:29

10:29

21250.98

21251.98

1.00

1.1033

1.1033

1.1033

2.7635

2.7752

177

27/02/14

10:05

11:05

21251.98

21252.98

1.00

1.1033

1.1033

1.1033

2.7391

2.7551

242

 

 

Monitoring Station                              :        TM-RA2                                                             

Date

Time

Elapse Time

Sampling Time (hrs)

Flow Rate (m3/min.)

Average (m3/min.)

Filter Weight (g)

Conc. (mg/m3)

Start

Finish

Initial

Final

Initial

Final

Initial

Final

04/02/1421/01/14

0913:1500

104:1500

2112680.98

2112781.98

1.00

1.2425

1.2425

1.2425

2.76362.7443

2.77882.7621

204231

06/02/1423/01/14

143:5045

154:5045

21151205.98

2115206.98

1.00

1.2425

1.2425

1.2425

2.77122.7503

2.79002.7651

252199

08/02/1425/01/14

10:015

11:015

21152206.98

21153207.98

1.00

1.2425

1.2425

1.2425

2.73432.7576

2.75122.7723

227197

11/02/1428/01/14

104:140

115:410

21177231.98

21178232.98

1.00

1.2425

1.2425

1.2425

2.77212.7487

2.78962.7658

235229

13/02/1428/01/14

1309:0055

1410:0055

21178232.98

21179233.98

1.00

1.2425

1.2425

1.2425

2.78022.7549

2.79662.7722

220232

15/02/1430/01/14

101:101

121:101

21179233.98

21180234.98

1.00

1.2425

1.2425

1.2425

2.76142.7486

2.77832.7671

227248

18/02/14

09:00

10:00

21258.98

21259.98

1.00

1.2425

1.2425

1.2425

2.7403

2.7561

212

18/02/14

10:20

11:20

21259.98

21260.98

1.00

1.2425

1.2425

1.2425

2.7588

2.7750

217

20/02/14

08:50

09:50

21260.98

21261.98

1.00

1.2425

1.2425

1.2425

2.7391

2.7561

228

22/02/14

08:25

09:25

21261.98

21262.98

1.00

1.2425

1.2425

1.2425

2.7688

2.7827

186

25/02/14

09:40

10:40

21286.98

21287.98

1.00

1.2425

1.2425

1.2425

2.7720

2.7862

190

27/02/14

10:10

11:10

21287.98

21288.98

1.00

1.2425

1.2425

1.2425

2.7522

2.7694

231

 

 

 


                                                                

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix B3

 

Graphical Plots of Impact Air Quality Monitoring Data

 

 

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix C1

 

Calibration Certificates for

Impact Marine Water Quality Monitoring Equipments

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix C2

 

Impact Marine Water Quality Monitoring Results

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix C3

 

Graphical Plots of Impact Marine Water Quality Monitoring Data

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix D1

 

Calibration Certificates for

Impact Noise Monitoring Equipments

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix D2

 

Impact Noise Monitoring Results

 


 

 

Day-time Noise Monitoring`

 

 

 

 

Monitoring Location: TM-RN1 *

 

Date

Start Sampling Time (hh:mm)

Noise Level dB (A)

Wind

Speed (m/s)

Weather Condition

Leq(30min)

L10

L90

2304/01/1402/14

13:0014:10

57.156.2

58.557.5

53.452.1

0.50.3

CloudyFine

0625/01/1402/14

13:0009:05

56.657.7

58.059.0

52.253.2

0.40.4

CloudyCloudy

1328/01/1402/14

11:0010:55

59.356.6

61.457.9

52.452.2

0.40.3

CloudyCloudy

1530/01/1402/14

11:0509:40

57.656.4

59.557.2

52.152.3

0.40.3

CloudyFine

18/02/14

09:10

57.4

59.0

53.2

0.3

Cloudy

20/02/14

08:50

57.7

59.2

53.4

0.3

Fine

25/02/14

09:18

59.3

62.4

52.8

0.4

Fine

27/02/14

13:30

57.2

58.4

53.3

0.3

Cloudy

Remark: Since Lands Department did not approve us to enter their own area where the noise monitoring stations TM-N1 and TM-N2 located due to the security, noise monitoring was carried out at noise monitoring stations TM-RN1 and TM-RN2 (refer to the figure 3 attached) in this reporting month.

 

 

 

 

Monitoring Location: TM-RN2 *

 

Date

Start Sampling Time (hh:mm)

Noise Level dB (A)

Wind

Speed (m/s)

Weather Condition

Leq(30min)

L10

L90

04/02/1423/01/14

13:0514:15

57.657.4

59.058.5

53.153.3

0.50.4

CloudyFine

06/02/1425/01/14

13:0509:10

57.157.4

58.658.6

52.854.0

0.40.4

CloudyCloudy

13/02/1428/01/14

11:0511:00

57.357.0

59.658.1

54.453.5

0.30.3

CloudyCloudy

15/02/1430/01/14

11:0209:45

55.757.0

57.458.1

51.352.9

0.50.4

CloudyFine

18/02/14

09:15

56.8

58.5

52.7

0.4

Cloudy

20/02/14

08:55

57.4

58.8

53.1

0.3

Fine

25/02/14

09:15

58.7

60.7

51.9

0.3

Fine

27/02/14

10:35

57.6

59.0

52.7

0.5

Cloudy

Remark: Since Lands Department did not approve us to enter their own area where the noise monitoring stations TM-N1 and TM-N2 located due to the security, noise monitoring was carried out at two noise monitoring stations TM-RN1 and TM-RN2 (refer to the figure 3 attached) in this reporting month.

 

 

 

 


.

 

 

 

 

 

 

 

 

 

 

 

 

Appendix D3

 

Graphical Plots of Impact Noise Monitoring Data

 

 

 

 

 

 

 

                                                                                             


 

 

 

 

 

 

 

 

 

 

 

 

Appendix E

 

Weather Condition

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix F

 

Event-Action Plans

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix G

 

Construction Programme

 


 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix H

 

Weekly ET’s Site Inspection Record

 


 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix I

 

Implementation Schedule of Mitigation Measures

 

 

 


Environmental Mitigation Implementation Schedule

 

 Environmental Protection Measures

Location

Implementation Status

Implemented

Partially implemented

Not implemented

Not Applicable

Air Quality

 

 

 

 

 

§Dust control / mitigation measures shall be provided to prevent dust nuisance.

All areas

Ö

Ö

 

 

§Water sprays shall be provided and used to dampen materials.

All areas

Ö

 

 

 

§All stockpile of aggregate or soil should be enclosed or covered and water applied in dry or windy condition.

All areas

Ö

 

 

 

§Any vehicle with open load carrying area used for moving materials which has the potential to create dust shall have properly fitting side and tail boards. Material having the potential to create dust shall not be loaded to a level higher than the side and tail boards, and shall be covered by a clean tarpaulin.

All areas

Ö

 

 

 

§Unpaved areas should be watered regularly to avoid dust generation.

Site Egress

Ö

 

 

 

§The designated site main haul road shall be paved or regular watering.

All haul roads

Ö

 

 

 

§The public road around the site entrance should be kept clean and free from dust.

All areas

Ö

 

 

 

§Wheel washing facilities including high-pressure water jet shall be provided at the entrance of work site.

Site Egress

Ö

 

 

 

§Every vehicle shall be washed to remove any dusty materials from its body and wheels before leaving the fill bank.

Site Egress

Ö

 

 

 

§The temporary slope surfaces shall be covered with impermeable sheet or sprayed with water.

All areas

Ö

 

 

 

§Vehicle and equipment should be switched off while not in use.

All areas

Ö

 

 

 

§All plant and equipment should be well maintained e.g. without black smoke emission.

All areas

Ö

 

 

 

§Open burning should be prohibited.

All areas

Ö

 

 

 

Noise Impact

 

 

 

 

 

§The approved method of working, equipment and sound-reducing measures (e.g. use of silenced type of equipment, etc.) shall be adapted.

All areas

Ö

 

 

 

§Only well maintained plant should be operated on-site and plant should be serviced regularly during the construction works.

All areas

Ö

 

 

 

§Powered mechanical equipment (PME) should be covered or shielded by appropriate acoustic materials.

All areas

Ö

 

 

 

§Air compressors and hand held breakers should have noise labels.

All areas

Ö

 

 

 

§Machines and plants that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum.

All areas

Ö

 

 

 

§Noisy equipment and mobile plant shall always be site away from NSRs.

All areas

Ö

 

 

 

 

 Environmental Protection Measures

Location

Implementation Status

Implemented

Partially implemented

Not implemented

Not Applicable

Water Quality

 

 

 

 

 

§The existing / realigned intercepting channels and the sand / silt removal facilities shall be used and maintained.

All areas

Ö

Ö

 

 

§Temporary intercepting drains should be used at the stockpiling area to divert polluted stormwater to the intercepting channels. Earth bunds and sand bay barriers shall be used to assist the diversion of polluted stormwater to the intercepting channels.

All areas

Ö

 

 

 

§The stormwater intercepting system shall be effective to collect of runoff and remove suspended solids before discharge.

All areas

Ö

 

 

 

§The material shall be properly covered to prevent washed away especially before rainstorm.

All areas

Ö

 

 

 

§Unnecessary water retained in receptacles and standing water should be avoided to prevent mosquito breeding.

All areas

Ö

 

 

 

§The temporary slope surfaces shall be covered with impermeable sheet or sprayed with water.

Temporary Slopes

Ö

 

 

 

§Existing and newly constructed Catchpits, sand and silt removal facilities and intercepting channels shall be maintained, and the deposited silt and grit shall be removed weekly and on a need basis especially at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times.

All areas

Ö

 

 

 

§A wheel washing bay shall be provided at the site exit and wash-water shall have sand and silt settled out or removed before being discharged into storm drains.

Wheel Washing facility

Ö

 

 

 

§The section of construction road between wheel washing bay and the public road shall be paved with concrete, bituminous materials or hardcores to reduce vehicle tracking of soil and to prevent site run-off from entering public road drains.

Site Egress

Ö

 

 

 

§Sewage from toilets shall be discharged in to a foul sewer, or chemical toilets shall be provided.

Site Office

Ö

 

 

 

§The chemical toilets (if use) shall be provided by a licensed contractor, who will be responsible for disposal and maintenance of these facilities.

All areas

Ö

 

 

 

§Tipping halls enclosed with top and 3-side to prevent spillage of material into marine water.

All areas

Ö

Ö

 

 

§Adequate environmental control measures shall be provided to prevent / avoid dropping of fill material into the sea during the transfer.

Along the seafront

Ö

 

 

 

§A waste collection vessel shall be deployed to remove floating debris.

Along the seafront

Ö

 

 

 

Landscape and Visual

 

 

 

 

 

·The maximum stockpiling height at the fill bank shall be limited to a maximum of +40mPD.

All areas

Ö

 

 

 

·Surface of outer slopes of the Fill Bank shall preferably be hydroseeded.

Completed slopes

Ö

 

 

 

·Stockpile of public fill shall be removed in a sequence to allow the outer hydrseeded to be removed later than other portions as far as practicable.

Completed slopes

Ö

 

 

 

·Casuarina equisetifolia were planted as buffer tree along the northern perimeter of the Site. The height of Casuarina equisetifolia was maintained at least 3m above soil level.

Site boundary

Ö

 

 

 

·Lighting shall be set to minimise night-time glare.

All areas

Ö

 

 

 

Waste Management

 

 

 

 

 

Construction Waste Management

 

 

 

 

 

·Relevant licence / permits for disposal of construction waste or excavated materials available for inspection.

All areas

Ö

 

 

 

·Excavated material to be generated from construction works to be re-used on-site as far as practicable to reduce off-site disposal.

All areas

Ö

 

 

 

·Mud and debris should be removed from waterworks access roads and associated drainage systems.

All areas

Ö

Ö

 

 

·Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.

All areas

Ö

 

 

 

·Prior to disposal of C&D waste, recyclable materials should be salvaged for reuse (such as wood and metal) and inert waste utilised as public fill to minimise the quantity of waste to be disposed of to landfill.

All areas

Ö

 

 

 

·In order to monitor the disposal of C&D material and solid wastes at public filling areas and landfills, and to control fly-tipping, a trip-ticket system should be included as one of the contractual requirements.

All areas

Ö

 

 

 

§Any soil contaminated with chemicals/oils shall be removed from site and the void created shall be filled with suitable materials.

All areas

Ö

 

 

 

Chemical Waste Management

 

 

 

 

 

·It is required to register as a chemical waste producer if chemical wastes would be produced from the construction activities.  The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and complied with for control of chemical wastes.

Waste Storage Area

Ö

 

 

 

·After use, chemical wastes (e.g. cleaning fluids, solvents, lubrication oil and fuel) should be handled according to the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

Waste Storage Area

Ö

 

 

 

·Spent chemicals should be stored and collected by an approved operator for disposal at the Chemical Waste Treatment Facility or other licensed facility in accordance with the Chemical Waste (General) Regulation.

Waste Storage Area

Ö

 

 

 

·Chemical wastes should be separated for special handling and appropriate treatment at the Chemical Waste Treatment Facility.

Waste Storage Area

Ö

 

 

 

·Chemical wastes including waste oil should be stored properly in designated areas, e.g. chemical waste storage area.

Waste Storage Area

Ö

Ö

 

 

·The designated chemical waste storage area should only be used for storing chemical wastes.

Waste Storage Area

Ö

 

 

 

The set-up of chemical waste storage area should

 

 

 

 

 

·Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition.

Waste Storage Area

Ö

 

 

 

·Be enclosed on at least 3 sides and securely closed.

Waste Storage Area

Ö

 

 

 

·Have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest.

Waste Storage Area

Ö

 

 

 

·Have adequate ventilation.

Waste Storage Area

Ö

 

 

 

·Be covered to prevent rainfall entering (water collected within the bund must be tested and disposal as chemical waste if necessary).

Waste Storage Area

Ö

 

 

 

·Be arranged so that incompatible materials are adequately separated.

Waste Storage Area

Ö

 

 

 

·Warning panels should be displayed at the waste storage area.

Waste Storage Area

Ö

 

 

 

·Waste storage area should be cleaned and maintained regularly.

Waste Storage Area

Ö

 

 

 

·Chemical waste should be transported by a registered chemical waste collector to a facility licensed to receive chemical waste.

All areas

Ö

 

 

 

·All generators, fuel and oil storage should be within bundle areas.

All areas

Ö

 

 

 

·Oil leakage from machinery, vehicle and plant should be prevented.

All areas

Ö

Ö

 

 

·In the event of chemical waste / dangerous goods / chemicals spillage or leakage, the procedures as outlined in the Spillage Response Plan should be followed.

All areas

Ö

 

 

 

·The dangerous goods / chemical spillage or leakage procedures (including equipments) should be in place.

All areas

Ö

 

 

 

Good Site Practices

 

 

 

 

 

·Nomination of approved personnel, such as site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site.

All areas

Ö

 

 

 

·Training of site personnel in proper waste management and chemical handling procedures should be provided.

All areas

Ö

 

 

 

·Good site practices should be adopted to clean the rubbish and litter on a regular basis so as to prevent the rubbish and litter from dropping into the nearby environment.

All areas

Ö

 

 

 

·Proper storage and site practices to minimise the potential for damage or contamination of construction materials.

All areas

Ö

 

 

 

·The Environmental Permit should be displaced conspicuously on site.

Site Entrance

Ö

 

 

 

·Construction noise permits should be posted at site entrance or available for site inspection.

Site Entrance

 

 

 

Ö

·Plan and stock construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste.

All areas

Ö

 

 

 

·Chemical storage area provided with lock and located on sealed areas.

Chemical Storage Area

Ö

 

 

 

·All chemicals should be placed at the banded area with adequate band capacity (>110% of largest tank).

Chemical Storage Area

Ö

 

 

 

·Any unused chemicals or those with remaining functional capacity should be recycled.

All areas

Ö

 

 

 

·Regular cleaning and maintenance programme for waste storage area, drainage systems, silt traps, sumps and oil interceptors.

All areas

Ö

 

 

 

·To encourage collection of aluminium cans by individual collectors, separate labelled bins should be provided to segregate this waste from other general refuse generated by the workforce.

All areas

Ö

 

 

 

·A recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be used, e.g. trip ticket system for chemical waste disposal. Quantities could be determined by weighing each load or other suitable methods.

All areas

Ö

 

 

 

·A collection area should be provided where waste can be stored and loaded prior to removal from site. An enclosed and covered area is preferred to reduce the occurrence of 'wind blown' light material. If an open area is unavoidable for the storage or loading/unloading of wastes, then the area should be bunded and all the polluted surface run-off collected within this area should be diverted into wastewater treatment system.

All areas

Ö

Ö

 

 

·Remove wastes in a timely manner.

All areas

Ö

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix J

 

Site General Layout plan

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix K

 

QA/QC Results of Laboratory Analysis

 


 

QA/QC Results of Laboratory Analysis of Total Suspended Solids

 

 

Sampling Date

QC Sample Analysis

Sample Duplicate

Sample Spike

% Recovery *

Sample ID

% Error #

Sample ID

% Recovery @

04/02/14

96.3

FC1-S

5.7

FM2-M

100.0

97.3

FM2-B

0.0

EM1-S

92.7

104.3

EM1-M

5.7

EC2-B

92.6

06/02/14

98.3

FC1-S

6.9

FM2-M

98.0

99.6

FM2-B

0.0

EM1-S

108.2

93.1

EM1-M

0.0

EC2-B

102.0

08/02/14

97.6

FC1-S

0.0

FM2-M

100.0

107.0

FM2-B

5.7

EM1-S

97.1

107.8

EM1-M

6.1

EC2-B

104.5

11/02/14

95.7

FC1-S

6.5

FM2-M

95.0

100.6

FM2-B

0.0

EM1-S

98.4

92.9

EM1-M

6.1

EC2-B

100.0

13/02/14

105.1

FC1-S

0.0

FM2-M

96.4

96.8

FM2-B

6.5

EM1-S

103.5

103.6

EM1-M

0.0

EC2-B

105.9

15/02/14

99.3

FC1-S

6.9

FM2-M

96.2

100.4

FM2-B

0.0

EM1-S

96.7

95.6

EM1-M

6.9

EC2-B

108.2

1821/01/1402/14

103.099.3

FC1-S

8.06.9

FM2-M

105.5103.3

93.893.1

FM2-B

0.00.0

EM1-S

104.6107.3

96.197.6

EM1-M

0.00.0

EC2-B

96.9100.0

203/01/1402/14

102.5103.6

FC1-S

0.06.9

FM2-M

90.3103.2

106.4103.5

FM2-B

8.05.7

EM1-S

100.0101.8

94.092.1

EM1-M

8.06.1

EC2-B

100.0104.5

225/01/1402/14

106.9106.3

FC1-S

0.00.0

FM2-M

92.9100.0

96.299.8

FM2-B

7.40.0

EM1-S

95.398.5

95.695.5

EM1-M

6.95.4

EC2-B

93.8101.9

258/01/1402/14

97.692.9

FC1-S

7.46.1

FM2-M

92.1102.9

105.292.3

FM2-B

6.50.0

EM1-S

98.592.7

97.097.7

EM1-M

6.95.4

EC2-B

96.3103.2

2730/01/1402/14

98.598.1

FC1-S

7.40.0

FM2-M

95.3105.5

108.0107.5

FM2-B

6.95.1

EM1-S

93.8108.2

107.1100.2

EM1-M

6.50.0

EC2-B

103.0101.6

 

Note: (*) % Recovery of QC sample should be between 80% to 120%.

(#) % Error of Sample Duplicate should be between –10% to 10%.

(@) % Recovery of Sample Spike should be between 80% to 120%.


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix L

 

 

Complaint Log

 


Complaint Log

 

Log Ref.

Location

Received Date

Details of Complaint

Investigation / Mitigation Action

Status

---

---

---

---

---

---

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figures